24.10.2009 |
EN |
Official Journal of the European Union |
C 256/27 |
Order of the Court of First Instance of 27 August 2009 — Abouchar v Commission
(Case T-367/08) (1)
(Non-contractual liability - EDF - Conditions for the grant and control of credits for an agricultural holding project in Senegal - Limitation period - Inadmissibility)
2009/C 256/49
Language of the case: French
Parties
Applicant: Michel Abouchar (Dakar, Senegal) (represented by: B. Dubreuil-Basire and J.-J. Lorang, lawyers)
Defendant: Commission of the European Communities (represented by: A. Bordes and E. Cujo, Agents)
Re:
Action for damages to compensate for the material and non-material harm allegedly suffered by the applicant as a result of the alleged errors of the Commission and its agents inherent in the conditions of grant and the control of loans financed by the European Development Fund (EDF) for its agricultural holding project in Senegal.
Operative part of the order
1. |
The action is dismissed as inadmissible. |
2. |
Mr Michel Abouchar is ordered to pay the costs. |